Site Transfer & Scale-Up

Manufacturing Site Transfer and Process Scale-Up

The same process on different equipment is a different process until you prove otherwise.

A manufacturing site transfer puts your process on new equipment, with new material lots and people who have never run it. We compare the two sites before anything moves, recalculate what depends on the machine or the batch size, and test the result in transfer batches. You find out what doesn't fit while it can still be changed on paper.

Clients served
800+
Countries
64
Production staff running a transfer batch on a commercial-scale granulation line

What breaks in a site transfer, and why

Settings copied from the old batch record

An impeller speed in rpm means nothing on a bowl of another diameter. Neither does a spray rate on a pan with a different number of guns. If the receiving site copies the number, it changes the process.

Materials that match on paper

Two grades of microcrystalline cellulose can meet one monograph and still flow differently. A new API source can have the same assay and another particle size. The specification may not cover the property your process relies on.

Steps nobody wrote down

The operator who stops the granulator by sound won't be at the new plant. We ask for these habits early. Then we turn each one into a measured end point, or show that it doesn't matter.

How a manufacturing site transfer runs, step by step

1. Gap analysis. WHO's 2022 guideline wants a qualified team on this, preferably with the quality units of both sites involved. We cover the areas it lists, including equipment, premises, utilities, cleaning, quality control, documents and computerized systems. We work from the documents and data both sites provide. Each gap gets a risk rating, an action and an owner.

2. Facility fit. We go through the process one unit operation at a time. Does the receiving machine work on the same principle? Is your batch inside its working volume? A granulator that is only a third full can be harder to fix than one that is too small.

3. Adapt and recalculate. For high-shear granulation we start from tip speed and compare the end point. For fluid beds it's air flow per plate area, for coaters spray rate against drying capacity, and for presses dwell time. These give a starting point. They don't replace a trial. Sterile products raise other questions: hold times before filtration, filter compatibility, fill accuracy, and whether a lyophilization cycle still holds in a dryer with different heat transfer.

4. Trial where the risk is. Some steps need an engineering or placebo batch first. Others can go straight to a transfer batch. We say which, and give the reason in the protocol.

5. Run transfer batches. The receiving site makes them under an approved protocol with acceptance criteria set in advance. We support the batches on site or remotely and record what happened, including what went wrong.

6. Compare, then decide. We put the results next to sending-site data: assay, impurities, uniformity and in-process trends, with dissolution profiles for oral solids. A batch can pass its specification and still look unlike the old product. If it does, we go back to step 3. If not, the process is ready for process validation.

What we assess

  • Equipment Comparison
  • Material Comparison
  • Utilities and Cleaning
  • QC Readiness
  • Transfer Batches

What you receive

  • Gap analysis each difference between the sites, with its risk, action and owner.
  • Fit table every unit operation, the machine at each site and whether the batch fits.
  • Adapted process description new settings with the calculation behind them.
  • Transfer batch protocol batches, sampling points and acceptance criteria agreed by both sites.
  • Transfer batch report results, deviations and a side-by-side comparison with the sending site.
  • Recommendation go to validation, or the changes needed first.

Guidance behind a site transfer

Inspectors can ask how you decided the new site was suitable. The gap analysis and the transfer protocol are your answer, so we write both to these references.

  • WHO TRS 1044, Annex 4 (2022) due diligence, gap analysis and the phases of a transfer. It revised the 2011 text (TRS 961, Annex 7).
  • ICH Q10 technology transfer as a lifecycle stage, supported by knowledge management.
  • ICH Q9(R1) the risk assessment used to rate gaps.
  • SUPAC-IR and SUPAC-MR how FDA grades changes in site, batch size and equipment for oral solids.
  • ISPE Good Practice Guide a working structure for transfer projects.

Who it's for

  • Companies adding a second manufacturing site
  • Product owners changing their CMO
  • CMOs taking on a client product
  • Licensees starting local manufacture
  • Plants moving to larger equipment

When companies move a process

Your CMO is closing a line, or you're leaving it. You want a second site so one plant can't stop supply. A licensee has to make the product locally. Or R&D has finished and the first commercial plant has different machines from the lab.

A larger granulator in the same building can raise the same questions. Nothing has moved, but the scale and maybe the operating principle have changed. For first scale-up during development, see scale-up and exhibit batches.

Why use a development team for a transfer

We also do formulation development, so we ask what each parameter is for before we try to match it. Some have to be held tightly. Others were simply what the first batch happened to use.

We can work between two companies that don't share much, such as an outgoing CMO and its replacement. Once the process runs, the same file feeds your transfer documentation.

Part of the Indivirtus group

Group companies
6
Clients across the group
800+
Countries
64

Frequently Asked Questions

What is a gap analysis in technology transfer? +

It's a structured comparison of the sending and receiving sites, done before the process moves. WHO TRS 1044 Annex 4 lists personnel, premises, equipment, utilities, cleaning, quality control, documentation, computerized systems, qualification, validation and waste among the areas to cover. Ours ends with a list of differences, each with a risk rating, an action and an owner.

How many transfer batches are needed before validation? +

No single number fits every transfer. Two sites with the same model of granulator and press may need one batch to confirm the settings. A change in operating principle may need engineering trials first. We set the number from the gap analysis and record the reasoning in the protocol. Validation (PPQ) batches come afterwards and are justified separately.

What if the receiving site has different equipment? +

It depends on how different. If the machine works on the same principle, we recalculate the settings and confirm them in a batch. If the principle changes, such as fluid bed granulation replacing high shear, the granule itself may change. That can mean development work, and SUPAC-IR treats a change to a different design and operating principle as a higher-level change.

Can we increase the batch size during a site transfer? +

You can, but each change makes a failed batch harder to explain. Where supply allows, we prefer to match the old batch size first and scale up next. For immediate-release oral solids, SUPAC-IR puts increases up to ten times the pilot or bio batch in Level 1, under stated conditions such as equipment of the same design and operating principle. Larger increases are Level 2.

How do you choose a receiving site? +

Start with the equipment: same operating principle, and a working volume that suits your batch. Next come cleaning capability, QC methods, warehouse conditions and the site's inspection history for that dosage form. If your product is potent or sensitizing, check containment first, because that alone can rule a site out. Once your agreement with the site is in place, we ask for its qualification records and review the documents. We do not perform the qualification ourselves.

What should the sending site hand over? +

At least the current batch record, process description, development report, specifications, test methods, stability data, deviation history and material supplier list. Recent batch data help more than a perfect procedure, because they show how the process really behaves. If some of it is missing, we record that as a gap and plan trials around it.

Show all 8 questions
Do you transfer sterile products as well as oral solids? +

Yes, both. For an aseptically filled product, the receiving site also has to show that its own line, people and interventions work, so process simulations (media fills) run there before transfer batches are released for use. Filter validation, container closure integrity and, for freeze-dried products, the cycle itself are reviewed as separate gaps.

Can you work between our current CMO and a new one? +

Yes. We collect the process knowledge from the outgoing CMO, agree responsibilities and the protocol with both sides, and follow open actions until they close. It helps to settle access to records in the contract before the notice period starts, because cooperation often drops once it does. Tell us where the discussion stands.